Inspection Types
The Office of Building Inspections performs the following inspections:
- Building
- Mechanical
- Electrical
- Plumbing
All inspection requests received prior to 8:30 am will be done that day. This includes inspection requests left on our voicemail.
We will make every effort to announce our presence to an occupied building. It is the responsibility of the applicant(s) to provide safe access to the property being inspected and to notify any person(s) or parties who may be in the occupied building during the inspection.
You must have the permit number and job address to request an inspection. Only the permit holder may request an inspection.
Inspection Types & Sequence
The list of inspections shown is a typical construction order. If there is a question about what inspection should be done at what time, please contact the Office of Community Development.
Inspection Type | Description / When Performed | Type Inspector |
---|---|---|
Temporary Electric | For temporary power while buildings are built | Electrical Inspector |
Footing | After installation of reinforcement and before placement of concrete | Building Inspector |
Foundation | After installation of concrete forms, reinforcement.Prior to placement of concrete | Building Inspector |
Plumbing Groundwork | After installation of below-slab plumbing piping and prior to covering with slab base material | Plumbing Inspector |
Electrical Groundwork | After installation of below-slab conduit and conductors in trenches or in slab base material and prior to covering with slab base material | Electrical Inspector |
Slab | After approval of all sub-trade ground work and after installation of reinforcement, vapor barrier and insulation.Before placement of concrete | Building Inspector |
Electrical Rough-In | Prior to concealment | Electrical Inspector |
Mechanical Rough-In | After installation of air handling duct, gas line testing (if applicable) and prior to concealment | Mechanical Inspector |
Plumbing Rough-in | Prior to concealment.Note:No air test allowed on plastic piping per Section 312.5 of the VA Plumbing Code | Plumbing Inspector |
Electrical Above-Ceiling (Commercial Primarily) | After installation of ceiling grid and prior to installation of ceiling tiles | Electrical Inspector |
Framing Above-Ceiling (Commercial Primarily) | To check fire walls/barriers, etc.After installation of ceiling grid and prior to installation of ceiling tiles | Building Inspector |
Water Line | Prior to backfilling trench, inspection from meter to building entry.Line must have tracer wire | Plumbing Inspector |
Sewer Line | Prior to backfilling trench, inspection from main line to building exit.Line must have tracer wire | Plumbing Inspector |
Framing | After approval of the electrical, plumbing, mechanical rough-ins | Building Inspector |
Insulation | After approval of all trade rough-ins and framing inspections | Building Inspector |
Backflow Device | After installation of backflow prevention devices and third-party inspection | Plumbing Inspector |
Air barrier | After installation of all air barrier components | Building Inspector |
Electrical Final | After completion of electrical system and prior to final building inspection | Electrical Inspector |
Mechanical Final | After complete installation of mechanical equipment and prior to final building inspection | Mechanical Inspector |
Plumbing Final | After complete installation of plumbing equipment and prior to final building inspection | Plumbing Inspector |
Building Final | After approval of the electrical, plumbing, mechanical and all other necessary inspections | Building Inspector |
-
Building Inspections
Physical Address
21 South Bruffey Street
Salem, VA 24153
Phone: 540-375-3036Fax: 540-375-4042
Inspection Requests
Phone: 540-375-3037
Hours
Monday through Friday
8 am to 4 pmHours for Inspectors
Monday through Friday
7 am to 4 pm